Find any Australian or New Zealand company or fund (dead or alive) by using SEARCH above or go directly to the site:
|
|
22 November 2024
Name: | REDBANK ENERGY LIMITED (AEJ) | ||||||||||||
Date of Listing: | 11 December 2006 | ||||||||||||
Date of Delisting: | 29 August 2016 | ||||||||||||
Former Names: |
|
Stock Exchange Status:
This entity was delisted from the Australian Securities Exchange on 29 August 2016.Legal Status:
Capital Gains Tax (CGT) Status:
This entity was deregistered on 02 October 2022. Deregistration is a Capital Gains Tax Event. In our opinion you are entitled to crystallise any capital loss in the tax year that deregistration occurs providing you have not previously done so. If you did not crystallise your loss in the tax year the entity was deregistered, you may seek to re-open that year’s assessment but anyway should seek professional advice as to how best to proceed.
Updates, corrections, disagreements please email to admin@delisted.com.au
Further information: deListed and InvestoGain are operated by Investogain Pty Limited which is licensed by ASIC as an Australian Financial Services Licensee (AFSL 334036). deListed acquires only securities that it deems to be of little or no value, in circumstances where the holder is unable to sell their securities on-market in the normal manner. This service has been provided online via the company’s website www.delisted.com.au since 2004.
Getting advice: Information provided in this section is of a general nature and applicable only to Australian tax residents who hold their investments on capital account (ie for long-term investment purposes). It has been prepared without taking into account your financial needs or tax situation. Before acting on the information, deListed suggests that you consider whether it is appropriate for your circumstances and recommends that you seek independent legal, financial, or taxation advice.
Disclaimer: The information provided above is to the best of our knowledge accurate as of today. But you should bear in mind that it is of a general nature and does not constitute financial or tax advice. Investogain Pty Limited accepts no liability for any loss arising from reliance on this information, including reliance on information that is no longer current.
Company | FROM | TO |
---|---|---|
REDBANK ENERGY LIMITED | 24/05/2011 | |
ALINTA ENERGY LIMITED | 21/03/2011 | 24/05/2011 |
ALINTA ENERGY GROUP | 04/01/2010 | 21/03/2011 |
BABCOCK & BROWN POWER | 04/01/2010 |
company deregistered today | 02/10/2022 |
delisted from the close of trading on Monday, 29 August 2016 pursuant to Listing rule 17.15. | 29/08/2016 |
we understand the company failed and was delisted because it did not pay its annual ASX listing fee | 29/08/2016 |
In response to shareholder enquiries, Redbank Energy Limited (ASX: AEJ) (REL) wishes to provide the following market update. Unfortunately, REL will be removed from the ASX official list on 29 August 2016. The immediate catalyst for delisting will be the non-payment of the 2016/17 ASX annual listing fee, which falls due on 27 August 2016. The reason for REL not paying the 2016/17 ASX listing fee is because REL will automatically be suspended on 9 October 2016 due to continual suspension. | 25/08/2016 |
Under listing rule 17.6, any entity (if not already suspended) that had not paid its annual listing fees by close of business on Monday 22 August 2016 will have its securities suspended from official quotation before the commencement of trading on Tuesday 23 August 2016. The company has not paid its annual listing fees in respect of the year ending 30 June 2017 but the securities are already suspended from official quotation. | 23/08/2016 |
Since the acquisition of the Redbank Power Station from the Receivers, REL has been progressing towards recommencing operations at the Redbank Power Station. There is still a significant amount of work to be undertaken to recommence operations at the Redbank Power Station and further updates will be provided regarding the process of this work and a likely date on which generation will commence in due course. | 13/05/2016 |
The REL consortium has entered into a number of agreements pursuant to which: a wholly owned subsidiary of REL, Biogreen Energy purchased the land, plant and equipment and water rights owned by Redbank Project for $5 milllion, purchase price was provided by a special purpose company; the water rights were transferred to the SPC; SPC and REL have entered into a put and call option over the water rights and SPC has granted REL a mortgage to secure performance of the call option; and addtional funds are to be advanced by the SPC to REL to commence the work to raise the funds needed to restart the operation of the Redbank Power Station. | 17/09/2015 |
The indicative offer for the acquisition of assets of the Redbank Power Station to the Receivers of Redbank Project was submitted as part of a consortium with the acquisition proposed to occur through a subsidiary of REL. The consortium has been selected the Receivers as the preferred bidder and will now proceed on an exclusive basis to negotiate final sale documentation. | 24/08/2015 |
REL submitted an indicative offer for the acquisition of the Redbank Power Station assets to the Receivers of Redbank Project, Korda Mentha. REL confirms that the sale process for those assets is on-going and REL remains involved in that process. | 15/07/2015 |
Redbank Energy Limited (ASX: AEJ) (REL) wishes to provide the following market update. Before the close of business today, Friday, 27 February 2015, REL will deliver to the receivers of Redbank Project Limited (Redbank Project), KordaMentha: a) REL's indicative offer for the acquisition of the assets of Redbank Project (REL Offer); and b) a signed Confidentiality Agreement in the terms negotiated and agreed between KordaMentha and REL. | 27/02/2015 |
ASIC has agreed to extend the period within which the company must hold its AGM from 30 November 2014 to 28 February 2015. | 02/12/2014 |
provides a market update in relation to Redbank Project Pty Ltd | 13/11/2014 |
provides a market update in relation to its statutory reporting obligations for the financial year ending 30 June 2014 | 30/10/2014 |
it is unbelievable that this company, suspended from quotation, has not released anything substantive to the market for a period of almost a year | 30/09/2014 |
the 2013 Annual General Meeting of the Shareholders of REL will be held as follows: TIME: 11.00am Sydney time DATE: Friday, 22 November 2013 PLACE: The Boardroom, Arnold Bloch Leibler, Level 24, Chifley Tower, 2 Chifley Square, Sydney, NSW, Australia | 22/10/2013 |
releases 2013 Annual Report to Shareholders | 22/10/2013 |
The securities of Redbank Energy Limited (the "Company") will be suspended from quotation immediately, at the request of the Company, pending the release of an announcement regarding its wholly owned subsidiary Redbank Project Pty Ltd. Security Code: AEJ | 09/10/2013 |
The suspension of trading in the securities of Redbank Energy Limited will be lifted upon the commencement of normal trading on Wednesday, 4 September 2013, in accordance with listing rule 17.8 following lodgement of its Appendix 4E for the year ended 30 June 2013. Security Code: AEJ | 03/09/2013 |
The securities of Redbank Energy Ltd will be suspended from Official Quotation from the commencement of trading today 2 September 2013 following failure to lodge their Periodic Reports for the period ended 30 June 2013 in accordance with Listing rules. | 02/09/2013 |
The suspension of trading in the securities of Redbank Energy Limited will be lifted upon the commencement of normal trading on Tuesday, 28 May 2013, in accordance with listing rule 17.8 following lodgement of its financial statements for the half year ended 31 December 2012. Security Code: AEJ | 27/05/2013 |
Redbank Energy Limited is aware of media reports suggesting that the owner of the Mt Thorley Warkworth mine is reviewing the viability of the mine following the Judgment which overturned the approval for the extension of the mine. However, Redbank Energy Limited has not received any communication from the mine owner regarding the impact of the Judgment and has no additional information that suggests that the mine owner will not continue to supply fuel in accordance with its agreements with Redbank Project | 22/04/2013 |
Redbank Redbank Energy Limited | ABN 67 116 665 608 Suite 2101B, 520 Oxford St, Sydney NSW 2022 | T + 61 2 8405 6810 | F + 61 2 8417 2660 www.redbankenergy.com Energy advises that its wholly owned subsidiaries Redbank Project Pty Ltd (Redbank Project) and Redbank Construction Pty Ltd (Redbank Construction) received at 3:16pm on 28 March 2013 a conditional proposal from its lenders (Syncora Guarantee Inc, Bank of Scotland International, KBC Bank and Commonwealth Bank of Australia (BankWest)) in relation to the deferral of the repayment of March principal and interest of approximately $7.6 million until 5:00pm (Sydney time) on 10 April 2013 (Proposed Deferral). The Proposed Deferral required the Redbank entities to respond by midnight on 28 March 2013 - If Redbank Project and Redbank Construction are unable to agree on a deferral with its lenders (assuming a deferral remains necessary following review of the arbitration award tomorrow), there is a risk that the Redbank entities may default under the relevant finance documents | 02/04/2013 |
advises of Change of Registered Office and Company Secretary | 05/03/2013 |
The securities of Redbank Energy Limited will be suspended from Official Quotation from the commencement of trading today 1 March 2013 following failure to lodge its Half Year Report and/or Accounts for the period ended 31 December 2012 in accordance with Listing rules. | 01/03/2013 |
The suspension of trading in the securities of Redbank Energy Limited (the "Company") will be lifted immediately, following receipt of a market update announcement | 09/02/2012 |
The securities of Redbank Energy Limited (the "Company"Â) will be suspended from quotation immediately, at the request of the Company, pending the release of an announcement. Security Code: AEJ | 02/02/2012 |
name changed from Alinta Energy Limited | 24/05/2011 |
we understand that on or about this date the company made a capital return of 10 cents per share | 18/03/2011 |
company deregistered today | 02/10/2022 |
delisted from the close of trading on Monday, 29 August 2016 pursuant to Listing rule 17.15. | 29/08/2016 |
we understand the company failed and was delisted because it did not pay its annual ASX listing fee | 29/08/2016 |
In response to shareholder enquiries, Redbank Energy Limited (ASX: AEJ) (REL) wishes to provide the following market update. Unfortunately, REL will be removed from the ASX official list on 29 August 2016. The immediate catalyst for delisting will be the non-payment of the 2016/17 ASX annual listing fee, which falls due on 27 August 2016. The reason for REL not paying the 2016/17 ASX listing fee is because REL will automatically be suspended on 9 October 2016 due to continual suspension. | 25/08/2016 |
Under listing rule 17.6, any entity (if not already suspended) that had not paid its annual listing fees by close of business on Monday 22 August 2016 will have its securities suspended from official quotation before the commencement of trading on Tuesday 23 August 2016. The company has not paid its annual listing fees in respect of the year ending 30 June 2017 but the securities are already suspended from official quotation. | 23/08/2016 |
Since the acquisition of the Redbank Power Station from the Receivers, REL has been progressing towards recommencing operations at the Redbank Power Station. There is still a significant amount of work to be undertaken to recommence operations at the Redbank Power Station and further updates will be provided regarding the process of this work and a likely date on which generation will commence in due course. | 13/05/2016 |
The REL consortium has entered into a number of agreements pursuant to which: a wholly owned subsidiary of REL, Biogreen Energy purchased the land, plant and equipment and water rights owned by Redbank Project for $5 milllion, purchase price was provided by a special purpose company; the water rights were transferred to the SPC; SPC and REL have entered into a put and call option over the water rights and SPC has granted REL a mortgage to secure performance of the call option; and addtional funds are to be advanced by the SPC to REL to commence the work to raise the funds needed to restart the operation of the Redbank Power Station. | 17/09/2015 |
The indicative offer for the acquisition of assets of the Redbank Power Station to the Receivers of Redbank Project was submitted as part of a consortium with the acquisition proposed to occur through a subsidiary of REL. The consortium has been selected the Receivers as the preferred bidder and will now proceed on an exclusive basis to negotiate final sale documentation. | 24/08/2015 |
REL submitted an indicative offer for the acquisition of the Redbank Power Station assets to the Receivers of Redbank Project, Korda Mentha. REL confirms that the sale process for those assets is on-going and REL remains involved in that process. | 15/07/2015 |
Redbank Energy Limited (ASX: AEJ) (REL) wishes to provide the following market update. Before the close of business today, Friday, 27 February 2015, REL will deliver to the receivers of Redbank Project Limited (Redbank Project), KordaMentha: a) REL's indicative offer for the acquisition of the assets of Redbank Project (REL Offer); and b) a signed Confidentiality Agreement in the terms negotiated and agreed between KordaMentha and REL. | 27/02/2015 |
ASIC has agreed to extend the period within which the company must hold its AGM from 30 November 2014 to 28 February 2015. | 02/12/2014 |
provides a market update in relation to Redbank Project Pty Ltd | 13/11/2014 |
provides a market update in relation to its statutory reporting obligations for the financial year ending 30 June 2014 | 30/10/2014 |
it is unbelievable that this company, suspended from quotation, has not released anything substantive to the market for a period of almost a year | 30/09/2014 |
the 2013 Annual General Meeting of the Shareholders of REL will be held as follows: TIME: 11.00am Sydney time DATE: Friday, 22 November 2013 PLACE: The Boardroom, Arnold Bloch Leibler, Level 24, Chifley Tower, 2 Chifley Square, Sydney, NSW, Australia | 22/10/2013 |
releases 2013 Annual Report to Shareholders | 22/10/2013 |
The securities of Redbank Energy Limited (the "Company") will be suspended from quotation immediately, at the request of the Company, pending the release of an announcement regarding its wholly owned subsidiary Redbank Project Pty Ltd. Security Code: AEJ | 09/10/2013 |
The suspension of trading in the securities of Redbank Energy Limited will be lifted upon the commencement of normal trading on Wednesday, 4 September 2013, in accordance with listing rule 17.8 following lodgement of its Appendix 4E for the year ended 30 June 2013. Security Code: AEJ | 03/09/2013 |
The securities of Redbank Energy Ltd will be suspended from Official Quotation from the commencement of trading today 2 September 2013 following failure to lodge their Periodic Reports for the period ended 30 June 2013 in accordance with Listing rules. | 02/09/2013 |
The suspension of trading in the securities of Redbank Energy Limited will be lifted upon the commencement of normal trading on Tuesday, 28 May 2013, in accordance with listing rule 17.8 following lodgement of its financial statements for the half year ended 31 December 2012. Security Code: AEJ | 27/05/2013 |
Redbank Energy Limited is aware of media reports suggesting that the owner of the Mt Thorley Warkworth mine is reviewing the viability of the mine following the Judgment which overturned the approval for the extension of the mine. However, Redbank Energy Limited has not received any communication from the mine owner regarding the impact of the Judgment and has no additional information that suggests that the mine owner will not continue to supply fuel in accordance with its agreements with Redbank Project | 22/04/2013 |
Redbank Redbank Energy Limited | ABN 67 116 665 608 Suite 2101B, 520 Oxford St, Sydney NSW 2022 | T + 61 2 8405 6810 | F + 61 2 8417 2660 www.redbankenergy.com Energy advises that its wholly owned subsidiaries Redbank Project Pty Ltd (Redbank Project) and Redbank Construction Pty Ltd (Redbank Construction) received at 3:16pm on 28 March 2013 a conditional proposal from its lenders (Syncora Guarantee Inc, Bank of Scotland International, KBC Bank and Commonwealth Bank of Australia (BankWest)) in relation to the deferral of the repayment of March principal and interest of approximately $7.6 million until 5:00pm (Sydney time) on 10 April 2013 (Proposed Deferral). The Proposed Deferral required the Redbank entities to respond by midnight on 28 March 2013 - If Redbank Project and Redbank Construction are unable to agree on a deferral with its lenders (assuming a deferral remains necessary following review of the arbitration award tomorrow), there is a risk that the Redbank entities may default under the relevant finance documents | 02/04/2013 |
advises of Change of Registered Office and Company Secretary | 05/03/2013 |
The securities of Redbank Energy Limited will be suspended from Official Quotation from the commencement of trading today 1 March 2013 following failure to lodge its Half Year Report and/or Accounts for the period ended 31 December 2012 in accordance with Listing rules. | 01/03/2013 |
The suspension of trading in the securities of Redbank Energy Limited (the "Company") will be lifted immediately, following receipt of a market update announcement | 09/02/2012 |
The securities of Redbank Energy Limited (the "Company"Â) will be suspended from quotation immediately, at the request of the Company, pending the release of an announcement. Security Code: AEJ | 02/02/2012 |
name changed from Alinta Energy Limited | 24/05/2011 |
we understand that on or about this date the company made a capital return of 10 cents per share | 18/03/2011 |
Your browser may reflect a date of printing in American format.
The phone number listed on Google doesn\'t appear to have any connection with Redbank Energy anymore. | 26/10/2022 15:59:03 |
I\'ve recevied an email from Link Market Services: \"Link are no longer the registry for Redbank effective 10 October 2018. Unfortunately we do not have any current contact details for Redbank Energy.\" | 25/11/2021 09:52:13 |
I hear Richard Butler has left Redbank, are there any other contact details for Redbank? | 07/06/2021 16:24:03 |
email: richard.l.butler @ gmail.com | 18/02/2021 16:15:20 |
Richard Liam Butler, Chairperson and Company Secretary, Redbank Energy Limited (ACN 116 665 608) Registered office & principal place of business Suite 2101B OR Suite 2105 T: 02 8405 6810 OR T: 02 9386 4355 email: | 18/02/2021 16:14:08 |
Tell your accountants these are worthless shares and only good to sell for a nominal $1 if you wish to crystallise a capital loss. | 16/11/2019 05:45:54 |
I need proof of holding for the accountants and am having no luck contacting Richard Butler or anyone else who is willing to help. Any help appreciated | 14/11/2019 13:35:57 |
Is there a declaration? | 27/11/2018 14:45:28 |
Any update on capital loss? | 22/08/2017 10:25:09 |
Any update on Capital loss | 12/10/2016 16:13:54 |
NAME | TITLE | DATE OF APPT |
---|---|---|
Richard Butler | Chairman, Company Secretary | 13/07/2011 |
Jeff Dimery | CEO | |
Vlad Artamonov | Non Exec Director | 15/08/2011 |
Simon Maher | Non Exec Director | 13/07/2011 |
Todd Plutsky | Non Exec Director | 12/08/2011 |
Date of first appointment, title may have changed.
Date of first appointment, title may have changed.
Contact Us | Financial Services Guide | Privacy Policy
This website is owned and operated by Investogain Pty Limited.
ABN 88 129 443 447 | AFSL 334036
Information provided is of a general nature and not for trading or advice.
Copyright © 2002-2024 Investogain Pty Limited. All rights reserved.